This working group focusses on the communication between the charging station (EVerest) and the management system(s) (CPMS)


...

Meeting Notes:


26 June 2024

Development update:
- Variable Monitoring work is progressing, first parts are merged
- Some minor updates
- Smart Charging: JOET is working on Smart Charging, to get to a base that can merged in.
 

EVerest release 2024.6: 
  Feature Freeze expected today. 
  Starting two week test period.


Updated the OCPP roadmap


Discussion on Composite Schedules.
  How to take local and minChargingRate into account.
  Currently libOCPP calculates a CompositeSchedule and send that the the EnergyManager. 
  libOCPP calculates profile per EVSE, it does the load balancing.
  EnergyManager does not get ChargePointMaxProfile, minChargingRate etc.
  So it cannot take these parameters into account when it needs to limit below the CompositeSchedules given by libOCPP.
  JOET will make a proposal for a solution.


05 June 2024

Discussed:

  • Smart charging implementation collaboration until July


29 May 2024

Discussed:

  • Couple of OCPP issues that have come up last weeks:
    • ACPhaseSwitchingSupported
    • 15118 certificate per EVSE: Solved in OCPP 2.0.1 edition 3 on page 
    • 2.0.1: MonitoringBase: Switching monitoring base not 100% clear: different terms used: delete, clear, discard customer monitors. All mean: delete.
    • OCPP 1.6: Rounding meter values

Topics for the agenda next week:

  • OCPP roadmap/timeline


22 May 2024

Discussed:



08 May 2024

Discussed:



  • Discussed the problem found with root certificates in folders.
      More background info. Certificate is printed, but only the old one.
      Might not even have worked before.
     
  • Discussed how to handle 15118 V2G certificate per SECC in case of multiple EVSE. OCPP certificate handling does not seem to support this where 15118-1 gives both options. 


02 May 2024

Discussed:


17 April 2024

Discussed:

  • Database Migrations now merged. Documentation added to explain how it works. When migrating to this version the first version needs manuel work. After this it will be automatic.
  • Size of PRs. Larger or small, pros and cons
  • Discussed meeting format: stick to weekly. Try to discuss ongoing on next planned use cases.


10 April 2024

Discussed:

  • OCPP 2.0.1 status document merged. When adding new OCPP 2.0.1 features, please update the document.
  • Pull request for database migrations is open. Developer documentation will be added.
  • Discussed how to handle custom data fields.

...