Concept of scheduling LN: IEC61850-90-7 (figure 13)


  • Part of software defined substation / centralised control and protection

North: 104/61850

South: not known yet


  • Local configuration collection and storage (what configs are running in the substation)

North/south: yet unknown, depends on the vendor


  • Test local configurations

South: 61850


  • Collect and redispatch fault recordings

Collect COMTRADE files from IED's
South: COMTRADE / PQDIFF

North: unkown


  • Ad-hoc fault recording control

South: probably IEC61850